Soft afternoon light on a quiet sandy inlet shore, with tawny dune grass, blue-green tidal water and a low offshore sand shoal.

New Topsail Inlet Goes Into Winter Between Dredges, With Its Bar Buoys Listed Missing

On a nautical chart, Banks Channel behind Topsail Beach is drawn as a marked route of daybeacons and buoys. The bar channel at New Topsail Inlet just south of it has no buoys on the chart. NOAA's Coast Pilot, in the edition dated Nov. 1, 2026, explains why.

"The buoys marking the bar channel are frequently shifted in position to mark the best water and therefore not charted; caution is advised. The inlet should not be entered by strangers."

On the bar, only the buoys mark the channel, and they get moved as the shoals move. As of the Coast Guard's most recent weekly notice, most of them are not where they belong. The town's next dredging project is roughly a year away. So through this winter, the current record of the inlet is a weekly federal list, and anyone running the inlet from Topsail Beach should read it.

What the Nov. 4 notice lists at the inlet

The Coast Guard publishes a weekly Local Notice to Mariners for its East District. The issue dated Nov. 4, 2026 includes a discrepancy list, which is the Coast Guard's record of aids that are missing, damaged, or off station. These are the Topsail Beach entries:

Aid Status in the Nov. 4, 2026 notice
New Topsail Inlet Buoy 1 Missing
New Topsail Inlet Buoy 2 Buoy damaged
New Topsail Inlet Buoy 3 Missing
New Topsail Inlet Buoy 4 Missing
New Topsail Inlet Buoy 5 Missing
New Topsail Inlet Buoy 7 Off station
Banks Channel Daybeacon 19 Structure destroyed
Old Topsail Creek Buoy 6 Signal malfunctioning; relocated for dredging
Old Topsail Creek Buoy 7 Relocated

Buoy 5 has been missing for a while. A Coast Guard bulletin sent Sept. 3, 2026 first reported it missing, and two months later the November notice still does. Statuses can change from one week to the next. A buoy that is reset shows up in a later notice, so the Nov. 4 table reflects that week and should be checked against the newest issue.

Offshore, the approach is marked by the New Topsail Inlet Lighted Whistle Buoy "NT," LLNR 795. The current Light List places it at 34-20-11.703N, 077-38-26.765W, with a Morse "A" sound signal. The same Nov. 4 notice carries an advance notice that the Coast Guard plans to remove NT's whistle when it replaces the buoy's hull. The notice says the change may not happen right away.

Why the buoys carry so much weight here

New Topsail Inlet is a federal navigation project. The U.S. Army Corps of Engineers Wilmington District lists it as a 1966 modification of the Atlantic Intracoastal Waterway. The authorized dimensions are an 8-foot-deep, 150-foot-wide channel from the ocean to the gorge and a 7-foot-deep, 80-foot-wide connector to the waterway. Those are the depths the project is designed for. Actual depths depend on how long it has been since the last dredge.

The Coast Pilot says the channels behind the inlet, which run northeast through Topsail Sound and northwest through Howards Channel to the waterway, are "subject to continual change and aids mark the best water; local knowledge is advised." When shoals move, the Coast Guard moves the marks to follow the deeper water. On this bar, each buoy is one of the few public reference points for where the channel is, so a missing one leaves a gap the chart cannot fill.

Two surveys from this fall add to the picture. The Corps' inlet survey index includes a Topsail Inlet hydrographic survey dated Aug. 24, 2026. Its map notes that the soundings show conditions only on the survey date and that shoaling can change them quickly. The town's coastal engineers at TI Coastal surveyed from Sept. 29 to Oct. 23. The survey covers the waterway, Topsail Creek, Howard's Channel, the connector channel, Banks Channel, side channels, and Topsail Inlet, with depths in feet relative to mean low water. The town posted that survey on Oct. 29. The survey itself says the aid positions shown were observed on Oct. 14 and may have changed since.

The dredge calendar runs through a May bid and a fall start

The town's most recent completed inlet project began in November 2023. Norfolk Dredging dredged New Topsail Inlet and put the sand on the beach. Dredging Today reported that the work finished on Feb. 26, 2024, after more than 1.5 million cubic yards were dredged and at least 1.3 million cubic yards were placed on the beach. The town's beach nourishment page still lists that 2023 to 2024 project as its latest.

The next project was discussed at the town's Beach, Inlet and Sound committee meeting on Oct. 15, 2026, which is posted on video. TI Coastal's representative laid out this sequence:

  1. A cost estimate for next year's project goes to the state's shallow-draft fund within weeks of the meeting.
  2. Permitting picks up around December.
  3. The goal is to have the project ready by May, when dredging companies would bid.
  4. A contract would follow, with work starting in the fall.

He said he had already told dredging company executives at an industry conference in Wilmington to look for a May bid from Topsail Beach for about 1 million to 1.2 million cubic yards. That would be a somewhat smaller job than the more than 1.5 million cubic yards Norfolk Dredging removed in 2023 and 2024. Even if everything stays on schedule, the inlet goes through this winter, next spring, and next summer's boating season on the channel that exists now.

How the work gets paid for is also changing at the state level. According to the Corps' fact sheet, a North Carolina agreement that let state and local money pay the Corps for maintenance dredging has been the main funding source for work at Bogue Inlet, Carolina Beach Inlet, Lockwoods Folly River, and New Topsail Inlet. A Division of Water Resources presentation from April 23, 2026 says the 2016 amendment raised the annual cap to $12 million, that the agreement "ends in 2026," and that the state submitted a letter of intent for a new long-term agreement in March 2026. The same presentation lists "Topsail Inlet (Pender County)" among non-federal projects, which the state funds through grant contracts with the municipality. That is the route the town's consultant described for next year's project. As a general estimate for repeat projects, the presentation gives Topsail "$16,000,000 every 4 years."

Where the November fish are, relative to the bar

This matters most to boaters because of where the fish are this month. The Fisherman's Post Topsail and Sneads Ferry report, posted Nov. 1, 2026, splits the fishing between inside water and water you reach through the inlet.

Inside the inlet, in the sound and creeks:

  • Speckled Specialist Charters reported many smaller speckled trout with some fish up to 28 inches. Productive depths ran from 4 to 16 feet, most often 4 to 8.
  • Native Son Guide Service said cooler nights should shift the area into "trout mode" and suggested the deeper 5- to 8-foot seams in the main creeks.
  • Carolina Flats Fishing described a "last blitz" of red drum on oysters and grass banks before bait thins out inshore.

Through the inlet and offshore:

  • South End Adventures put the nearshore king mackerel at 8 to 12 miles out, gag grouper at 10 to 20 miles, and expected black sea bass to pick up at 5 to 15 miles as the water cools.
  • Plan 9 Charters reported quality kings in 50 to 60 feet of water and bottom fish in 60 to 80 feet or more.

From the beach, Jolly Roger Pier reported scattered speckled trout and better bottom fishing for Virginia mullet and spot at night. East Coast Sports said the piers had caught some red drum over 32 inches, mostly on the north end of the island. A Topsail.Fish summary from Nov. 4 said persistent wind had made oceanfront fishing harder.

The trout and red drum fishing happens in water the Coast Pilot calls well marked. The kings, grouper, and sea bass are all on the other side of the bar, where the notice lists most of the buoys as missing.

Checking before the ramp

The town scheduled Bush Marina's boat ramp to close for maintenance for the week beginning Monday, Nov. 2, according to its Oct. 16 notice. The town's news page posts updates like that. For the inlet itself, the Coast Guard posts the weekly Local Notice to Mariners on the Navigation Center site. New Topsail Inlet Buoys 1 through 5 and 7 appear under the Banks Channel and New River–Cape Fear River headings in the discrepancy section. The Coast Pilot covers the inlet in chapter 5 of Volume 4, and its advice for the bar is "caution and local knowledge."

For waterfront owners on Banks Channel and Topsail Sound, the inlet's condition affects how a dock gets used year-round, not just in fishing season. If you want to talk through what the channel schedule means for a sound-side property you own or are considering, Lake to Coast Real Estate can walk through it with you. Schedule a Consultation with Neal.

Let’s Get Started

With 25 years of experience across law, sales, construction, and real estate, I guide clients with the strategy, skill, and insight they deserve.

Follow Me on Instagram